# Calculating Overall Equipment Effectiveness
- URL: https://www.pesec.no/calculating-overall-equipment-effectiveness/
- Published: 2016-04-02T09:00:00.000Z
- Updated: 2020-02-18T13:03:52.000Z
- Description: Watch this short example and learn how to calculate Overall Equipment Effectiveness (OEE).
- Author: Bruno Pešec
- Tags: Lean, #The Lean Presentation

Watch this short example and learn how to calculate Overall Equipment Effectiveness (OEE).

As we’ve learned [here](https://www.pesec.no/overview-of-the-overall-equipment-effectiveness/), OEE is a metric which integrates availability, performance and quality metrics.

Formulae needed for OEE calculation are:

> OEE = Availability x Performance x Quality

> Availability = Operating Time / Planned Production Time

> Performance = (Total Pieces / Operating Time) / Ideal Run Rate

> Quality = Good Pieces / Total Pieces

Don’t forget to check your measurement units!

---

****Want to know more?**

Vorne Industries offers their [OEE Pack](https://www.oee.com/free-oee-tools.html?ref=pesec.no#download-free-tools) for free, which includes:

- OEE Training Guide
- OEE Pocket Guide
- Calculating OEE Worksheet
- Calculating OEE Spreadsheet (xls)
- Top 25 Lean Tools
- Seven Deadly Losses

All the materials are concise and to the point so you can immediately start with your OEE calculations.

Jasiulewicz—Kaczmarek, et al ([2014](https://www.czasopismologistyka.pl/artykuly-naukowe/send/315-artykuly-na-plycie-cd-4/5858-artykul?ref=pesec.no)), present several different ways to calculate OEE and a case study. Vijayakumar and Gajendran ([2014](http://www.mtmgroup.it/wp-content/uploads/2014/11/Improvement-of-Overall-Equipment-Effectiveness.pdf?ref=pesec.no)) present a case study from injection moulding process industry, detailing how they calculated and improved OEE.

****References**

Jasiulewicz—Kaczmarek, M., Drozynerz, P., Kolmasiak, C. and Szczuka, M., 2014\. Analysis of performance by overall equipment efficiency – case study. *International Journal of Operations & Production Management*, 20(12), pp.1488-1502.

Vijayakumar, S.R. and Gajendran, S., 2014\. Improvement of overall equipment effectiveness (OEE) in injection moulding process industry. *IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)*, pp.47-60.

*This post was originally written for [The Lean Presentation](https://www.pesec.no/the-lean-presentation/).*